Problematic water mains being replaced in the Beaumount area
Uisce Éireann, working in partnership with Cork City Council, is replacing almost 1km of problematic water mains on Beaumont Drive with new modern pipes.
The works will commence in the week beginning August 30, 2021 and form part of Uisce Éireann's National Leakage Reduction Programme. The project will also involve laying new water service connections from the public water main in the road to customers' property boundaries and connecting it to the customers' water supply. Where the existing service connections on the public side are lead, these will be replaced as part of this improvement work.
Outlining the benefits the mains replacement will bring, Steven Blennerhassett from Uisce Éireann, explained: "The upgrading of these water mains will benefit the local community in Beaumount by strengthening and reinforcing the water network, and minimising disruptions in their water supply by reducing leakage and unplanned outages when bursts occur on the existing main."
This project is one example of how Uisce Éireann is working in partnership with Local Authorities to provide a more reliable water supply and reduce leakage. Fixing leaks can be complicated but Uisce Éireann are making progress. In 2018 the rate of leakage nationally was 46%, by the end of 2020 it was reduced to 40%. We are currently on course to achieve a national leakage rate of 38% by the end of 2021.
Steven added: "To facilitate the safe delivery of the upgrades, there will be some traffic management in place, however local and emergency access will be maintained at all times.
"A stop-go traffic management system may be in place and will be limited to short sections to minimise impact on customers. During this project there may be some short-term water outages and the project team will ensure that customers are given a minimum of 48 hours' notice prior to any planned water outages.
"We understand that road works and water outages can be inconvenient, but our crews will make every effort to minimise disruption to local communities as we continue to improve the water supply in Cork and progress the National Leakage Reduction Programme."
The works will be carried out on behalf of Uisce Éireann by Ward and Burke Limited and are expected to be completed by mid-November.
The National Leakage Reduction Programme helps provide a more reliable water supply to Irish communities by reducing high levels of leakage and improving water quality. Its delivery represents an investment of over €500 million between 2017 and the end of 2021 to reduce leakage and replace old pipes on the water network.
For more information on reducing leaks visit our National Leakage Reduction Programme project page.
Our customer care helpline is open 24/7 on 1800 278 278 and customers can also contact us on Twitter @IWCare with any queries. For updates please visit the Supply and Service Updates section or set your location on our website.
Uisce Éireann continues to work at this time with our Local Authority partners, contractors and others to safeguard the health and well-being of both staff and the public and to ensure the continuity of critical drinking water and wastewater services. Uisce Éireann would like to remind people to follow the HSE COVID-19 advice and ensure frequent handwashing.